What are the installation instructions for the Shale Shaker
Each solid phase control system must have enough Shale Shaker to ensure 100% circulation processing rate of drilling fluid. When using, first refer to the manufacturer's user guide for correct installation, operation and maintenance. If the operation manual is not applicable, the following guidelines may be helpful for proper use.
(1) If the installation of the flow line is too low, it will cause the accumulation of drill cuttings. The angle of the flow line must be considered to prevent solid phase accumulation, and the slope of the flow line can be reduced by every 10th.
(2) When a reflux tank (reserve tank) is used, the process line should enter its bottom to prevent solid phase accumulation. If the flow line design enters from the top, there must be a connecting pipe extending to the bottom.
(3) There must be enough space and passages on site for inspection and maintenance of the vibrating screen.
(4) The formation of T-shaped branch flow lines must be avoided. The solid phase always chooses a straight flow line to move, which will cause uneven distribution of the solid phase transported to the Shale Shaker.
(5) When using multiple vibrating screens, ensure that the liquid and solid phases are evenly distributed.
(6) The optimized top conveying process can prevent the accumulation of drill cuttings in the storage tank.
(7) Cement sideways should be designed around the outside of the circulation system.
(8) The installation position and operating platform of the vibrating screen must be level. If this condition is not met, the solid phase and liquid phase handling capacity will decrease.
(9) The motor and starting device must be explosion-proof. Local electricity regulations must be followed. It must be ensured that the size of the starting heating device is appropriate.
(10) Provide suitable voltage and frequency. Too low voltage will reduce the service life of the electrical system, and too low frequency will reduce the processing capacity of the Mud Shale Shaker.
(11) Adjust the correct number of motor revolutions.
(12) Adjust the correct vibration mode of the Shale Shaker surface.
(13) Adjust the tightness of the transmission belt according to the instructions for use.
(14) The screen cloth must be installed in accordance with the operating instructions.
(15) Prepare the flushing system to clean the equipment.
(16) If a water spray pipe is installed, the water must be controlled to spray out in a mist, not a stream of water.
Xi'an HL produces various Shale Shaker, which can also be customized according to customer needs, welcome to send inquiry to us: sales@hlsolidscontrol.com if you want to know more about it.