• Solids Control EquipmentMud Shale Shaker Degasser Mud Cleaner Centrifuge Mud Agitator Mud Gun Jet Mud Mixer Centrifugal Pump Shear Pump Spray Pump Vacuum Pump Mud Gas Separator Ignition Drilling Cuttings Dryer Filter Press Conveyor
  • Mud Treatment SystemDrilling Fluid Solids Control System Water-based Mud Treatment System Oil based Mud Treatment System Trenchless Mud Treatment System Mud Mixing System Drilling Fluid Cooling System Truck mounted Mud Circulation System Barite Recovery System
  • Tank and Steel StructureRig Mat Elevated Diesel Tank Nested Water Tank Fracturing Fluid Tank Drilling Pipe Basket Drill Cuttings Box Mud Storage Tank
  • Drilling Tools and Spare PartsMud Shale Shaker Spare Parts Centrifugal Pump Spare Parts Mud Pump Spare Parts Centrifuge Spare Parts Mud Tank Bottom Valve Mud Hopper Mud Tank Level Alarm Polyurethane Cyclone Electric Motor WPS Reducer Mud Tank Union Explosion-proof Water Tank Heater
  • ApplicationOilfield DrillingGas Geothermal DrillingTrenchless HDDDrilling Waste TreatmentSewage TreatmentTunnel ShieldTailings Dry Discharge
  • Contact us
    WhatsApp: 86-13735815206 / 86-17392256505
    WeChat: 86-13735815206 / 86-17392256505
    Phone: 86-29-88680837
    Mail: sales@hlsolidscontrol.com
    Add: Room 804, Building 1, Western Cloud Valley Phase II, Fengxi New Town, Xixian New District, Shaanxi Province

    How to install the shear mixing device?

    Time: 2023-08-02 Source: Author: hlsolidscontrol
    Installing a shear mixing device is a process that involves placing the equipment, connecting pipes and connecting power. So how to install the shear mixing device:
    1. Foundation preparation:
    According to the site conditions, level the foundation at an appropriate position to ensure that the foundation is at the same level as the mud tank foundation. This ensures that the device is stable and not prone to tipping or wobbling.

    2, Equipment placement:
    Place the shear mixing device on the prepared foundation, making sure the equipment is level. You need to choose a suitable placement according to the size and weight of the equipment.
    shear mixing device  shear mixing device factory
    3. Pump suction connection:
    Use a rubber hose to connect the suction port of the pump to the mud tank. Make sure the connections are tight to prevent leakage or air bubbles from entering the system.

    4. Power on:
    Plug the device into the correct electrical outlet and turn on the power. Before connecting the power, make sure the power switch of the device is off.

    5. Check shear pump steering:
    In some shear mixing devices, the steering of the pump is very important to ensure that the slurry is properly sheared and mixed. Therefore, after turning on the power, move the switch to observe whether the steering of the shear pump is correct. If the steering is incorrect, it is necessary to change the connection method of the power phase wire until the steering is correct.

    6. Run the test:
    After confirming that everything is installed correctly, the operation test of the equipment can be carried out. Turn on the shear mixing device, and observe whether the device works normally and whether the pump can suck and discharge mud normally. At the same time, make sure that the device is running stably without abnormal vibration or noise.

    7. Perform maintenance:
    Once the shear mixing device is installed and operating normally, regular maintenance and maintenance must be carried out in accordance with the equipment manual and manufacturer's requirements. This can ensure the long-term stable operation of the equipment and prolong the service life of the equipment.
    Tel: 86-29-88680837
    WhatsApp: 86-13735815206 / 86-17392256505
    WeChat: 86-13735815206 / 86-17392256505
    E-mail: sales@hlsolidscontrol.com
    Add: Room 804, Building 1, Western Cloud Valley Phase II, Fengxi New Town, Xixian New District, Shaanxi Province
    ©2023 Xi'an HL Petroleum Equipment Co., Ltd.